Hydrostatic & Pneumatic Procedure
Hydrostatic
testing is most often preferred over pneumatic testing because of safety considerations.
Water is the preferred fluid medium for hydrostatic testing. In addition to its relatively incompressible nature, it is also the safest
fluid because it is nontoxic and nonflammable and it remains in liquid form down to
atmospheric pressure unless heated above the boiling point. Water is readily and
economically
available. ASME B31.1, section 137.4.3, specifies water as the test fluid for
hydrostatic tests unless otherwise specified. ASME B31.3, section 345.4.1, also
specifies water as the test fluid for hydrostatic test unless there is the possibility of
freezing or damage from adverse effects of water on the piping or the process for which the piping system is designed. This section provides for other uses of other nontoxic liquids as long as the flash point exceeds 120F (49C). If hydrostatic testing
is being considered for a system that was designed for use of a gaseous medium as the process fluid, it must first be determined that the piping system will support
the weight of the test liquid or that the piping can be safely supported during the hydrostatic test.
● All gravity supports installed
● Proper pipe routing
● Correct valve type and orientation
● Vents and drains installed to allow proper filling and draining
recorded if required by the codes
● All required piping stress relief, weld examinations, and welding documentation
completed and acceptable
● Before the test is to be run, make certain, by reviewing the piping against the
P&ID and valve line-up sheet, that
● All equipment not to be tested is disconnected from the test or isolated by closed
valves or testing blinds
● Tagging and lockout of any valves used to isolate the test boundaries is in place
to protect both the testing personnel and any others who may be on site
● All non boundary valves in the test boundary are in the open position
● Expansion joints, if any, have required restraints to protect against damage from
the test pressure
● All springs have travel stops to protect against the weight of the test medium
● All test equipment is checked and all test connections are tight
For gas systems, additional gravity supports may be required temporarily to support the weight of the test liquid. Since requirements vary from project to project, the person responsible for the test will need to make a specific checklist of items for each project before testing can begin.
All joints, including welds and flanges, of the portions of the system to be tested are left uninsulated and exposed for examination during the test. Some insulation may be installed on the straight runs or previously tested piping. If the system is to include jacketed piping, the leak tests should be run before any jacketing is installed.
A flow water pump is substituted for the pressurizing water pump during the filling of the piping. The water source should provide clean chloride-free water. The system is filled from the bottom to facilitate the venting of all air in the portion of the piping system under test. For sloped piping systems, filling should be done against the slope. Vents must be located at all high points in the piping and should be open during the filling stage. Once it is determined the system is completely liquid filled the vents may be closed and a pressurizing water pump connected to the system in place of the flow pump. The pressurizing pump must have a capacity greater than the allowable leakage of the system. Leakage at the packing glands of valves and pumps is permissible by the codes and is necessary to preserve the life of the packing. However, if this leakage is so great that the test pressure cannot be controlled by being trapped, there will be a problem in running the test. It is not very practical to turn the pressurizing pump on and off to maintain the pressure close to the required level. One solution is to temporarily tighten all the packings to a greater compression than is normally used during regular operation of the system. It may also be necessary to tighten flanges, screwed connections, and other mechanical or gland-type joints to eliminate leakage.
Test pressure |
Test pressure |
Test pressure |
Examination |
Code |
Test type |
ASME B31.1 |
Hydrostatic1 |
1.5 times design |
Max allowable test |
10 minutes |
Design |
ASME B31.1 |
Pneumatic |
1.2 times design |
1.5 times design or |
10 minutes |
Lower of 100 |
ASME B31.1 |
Initial |
Normal operating |
Normal operating |
10 minutes or |
Normal operating |
ASME B31.3 |
Hydrostatic |
1.5 times |
Not to exceed yield |
Time to complete leak examination |
1.5 times |
ASME B31.3 |
Pneumatic |
1.1 times design |
1.1 times design plus |
10 minutes |
Design |
ASME B31.3 |
Initial |
Design pressure |
Design pressure |
Time to complete leak examination |
Design |
ASME I |
Hydrostatic |
1.5 times max |
Not to exceed 90 per- |
Not specified, |
Max allow |
ASME III |
Hydrostatic |
1.25 times system design |
Not to exceed stress |
10 minutes |
Greater of |
ASME III |
Pneumatic |
1.2 times system |
Not to exceed stress |
10 minutes |
Greater of |
ASME III |
Hydrostatic |
1.5 times system |
If minimum test pressure exceeded by
6 |
10 minutes or |
Greater of |
ASME III |
Pneumatic |
1.25 times system design |
If minimum test pressure exceeded by
6 |
10 minutes |
Greater of |
ASME III |
Hydrostatic |
1.5 times system |
If minimum test pressure exceeded by
6 |
10 minutes |
Greater of |
ASME III |
Pneumatic |
1.25 times system design |
If minimum test pressure exceeded by
6 |
10 minutes |
Greater of |
PIPING MATERIAL
TYPES OF VALVES
|
|
TYPES OF PUMP
TYPES OF DISTILLATION COLUMN
PDMS & E3D COMMANDS
TYPES OF STORAGE TANK | |
READ POST >> |
0 Comments: